Tafel Power

Which ERCOT Queue Capacity Has a Signed Interconnection Agreement?

June 2026 snapshot. 434 GW in queue. 134 GW with signed interconnection agreements. Breakdown by technology.

ercot · interconnection · reference-data

Kris Narayanan · Tafel Power · July 5, 2026 · 1 min read


A reference snapshot of the ERCOT interconnection queue as of the June 2026 GIS report, split by technology and by interconnection agreement status.

The queue totals 434 GW across 1,828 active projects. Of that, 134 GW, about 31 percent, carries a signed interconnection agreement. The gross number and the signed number tell opposite stories: the headline suggests oversupply, while the signed subset shows how much thinner the signed stack is.

ERCOT queue capacity by technology, total versus signed interconnection agreement
Source: ERCOT June 2026 GIS Report. Analysis: Tafel Power

Batteries lead the queue at 162.6 GW, but only 37.4 GW is signed. Solar is 151.6 GW with 63.3 GW signed. Gas is 69.7 GW with 14.6 GW signed, the lowest signed share of the four. Wind is 47.1 GW with 18.7 GW signed.

The pattern to carry forward: signed interconnection agreements are a better starting point than gross queue capacity for judging project maturity, though a signed agreement is not the same as delivered capacity. Gas, the principal dispatchable resource in the queue, has the widest gap between what is queued and what is signed.

Methodology

Figures are drawn from the ERCOT June 2026 GIS Report (Large and Small Gen, projects with a Full Interconnection Study requested) and reconciled against the source file before publication. "Signed IA" reflects the report's IA Signed field. Figures reflect the June 2026 snapshot and may have changed since.


Share on LinkedIn

Questions, corrections or disagreement on any of this are welcome: kris@tafelpower.com

More from Insights

July 2, 2026

When Faster Power Stops Being Expensive

The best way to energize early is not fixed. It moves with what your load earns, and on the illustrative case it changes twice: once at about $49 per MWh and again at about $114.

June 30, 2026

The Real AI-Power Risk Sits Downstream of the Megawatts

For anyone siting or financing AI infrastructure: new AI hardware arrives on a two-year cycle while the delivery infrastructure built for it is financed for decades. Firm megawatts are necessary but interchangeable; the harder thing to secure is delivery that can absorb several hardware generations without a major retrofit.