January 15, 2026
Gas, Not Renewables, Is Driving ERCOT's Queue Growth
For developers and large power buyers: the queue total keeps rising, but nearly every new gigawatt is a single fuel.
Original analysis for power infrastructure transactions, large-load strategy and investment decisions across US power markets. Each brief ends in a decision you can act on, states what would prove it wrong, and shows its working.
40 briefs · January 2026 to present
Most recent
The newest brief, published in full with its chart and its finding.
Sustained work
Two runs of briefs where the same screen is applied repeatedly, one inside ERCOT and one across markets. Written in order, so the method compounds rather than repeats.
The gas queue reads 69.7 GW. Only 8.8 GW of it is signed and near-term. Eight briefs, in order, on how that gap was established and why the headline number cannot be underwritten.
January 15, 2026
For developers and large power buyers: the queue total keeps rising, but nearly every new gigawatt is a single fuel.
February 18, 2026
For developers and infra funds: the project count fell through late 2025 while total requested capacity rose, so the average project is larger.
July 5, 2026
June 2026 snapshot. 434 GW in queue. 134 GW with signed interconnection agreements. Breakdown by technology.
July 6, 2026
For hyperscalers pricing offtakes and infra funds valuing platforms: the ERCOT gas that is both signed and near-term is smaller than either filter suggests.
July 7, 2026
For hyperscalers siting loads and infra funds valuing gas platforms: the signed, near-term gas that clears the screen is concentrated in West Texas and nearly absent from the DFW load pocket.
July 9, 2026
For hyperscalers and infra funds procuring firm power: when the screened merchant set sits with a countable number of counterparties, price discovery is shaped more by relationship, timing, and project-specific alternatives than by broad competition.
July 11, 2026
Apply the historical post-IA completion rate to signed gas and a conservative request-to-operation base-rate weight to unsigned gas, and 69.7 GW becomes about 17 GW on a completion-weighted basis.
July 13, 2026
For anyone screening ERCOT gas by interconnection status: a dedicated plant can be under contract to a named customer and still appear in the queue as unsigned and in study. Project Kilby shows why captive generation needs a separate diligence framework.
The same screen run across five markets between April and July: how much firm gas is really available, and where the answer is hiding. Ohio built its already, MISO put it in the utility plan, Northern Virginia is leaning on the existing fleet, West Virginia's lead is one project, and the second-largest signed queue is in Oklahoma.
April 30, 2026
For data centers weighing the Midwest: Ohio's queue shows almost no new gas, but it added 6.4 GW during the Utica boom and now pairs an existing fleet with low-cost Utica gas and top-tier demand.
May 14, 2026
For data centers and infra funds looking at the Midwest and Gulf: MISO's interconnection queue shows almost no signed, near-term merchant gas, yet Louisiana is building more new gas than any state in the country.
June 11, 2026
For hyperscalers and infra funds in PJM: Northern Virginia leads PJM in forecast data-center demand growth and has almost no signed, near-term merchant gas behind it.
June 25, 2026
For developers and data centers eyeing West Virginia: the state's headline gas number is real, but the screened set is tiny, and for some projects the practical path is self-supply or dedicated generation.
July 10, 2026
For data centers willing to look past the marquee markets: SPP holds more signed, near-term gas than PJM and MISO combined, mostly in Oklahoma and the Texas Panhandle.
Lane
Where you can actually build, what gates it, and how long it really takes.
September 3, 2026
Wisconsin's public record tells a 100 MW load which tariff it must take, how long the term is, what security it must post and the gates it must pass. It does not say what the next gate costs, and the first answer is directional rather than a megawatt and date.
July 19, 2026
Why Entergy is one of the few utilities able to build firm power at AI scale, what customers must fund, and how its regulated model compares with merchant ERCOT.
July 12, 2026
For hyperscalers, developers, and infra funds: the firm-power options that can actually connect before the gas-turbine backlog clears, ranked by how fast they deliver.
July 12, 2026
For hyperscalers and infrastructure investors: the interconnection queue contains nearly 2 TW of proposed capacity, most of it solar, wind, and storage. The scarce product for a 24/7 load is firm capacity, not annual clean energy.
Lane
What the asset earns, who captures it, and what the contract should say.
September 1, 2026
Not owning the plant is ordinary. What is not ordinary is one contract that assigns the construction cost, the exit value and the demolition bill to a named company, and leaves the carbon at commercially reasonable efforts and a funded study.
August 16, 2026
Gas moved by $39 to $59 a megawatt-hour over three years. Where that lands is a drafting choice, not a market fact.
August 16, 2026
Every large-load power deal sets a minimum the customer owes whether or not it draws. Everyone compares the percentage. What the percentage is a percentage of is what decides whether it protects anyone.
August 15, 2026
Four structures, read from the tariffs, the commission orders and the filings. Facts and sources only. The arguments are in the two briefs this supports.
August 6, 2026
What every part of the data center power supply chain actually reports, from utilities to software. The turbine maker, holding the acknowledged bottleneck, reports 18.8 percent on an EBITDA basis, against 27.5 percent operating at Eaton. Four parts of the chain disclose no separable return at all.
July 29, 2026
South32 spent six years trying to replace the power and wrote off $372 million seven months before the plant stopped. So the date was never the risk. The power simply could not be replaced, and no filing has a field for that.
July 23, 2026
Total storage revenue keeps rising, but largely because capacity is added faster than per-unit revenue falls. The underwriting error is treating a market revenue forecast as if it described your asset. What still earns depends on which edge an asset holds and how fast it erodes.
July 21, 2026
The right commitment structure is not universal. It depends on which side has alternatives, which inputs are scarce, and how much unrecoverable exposure each milestone creates.
July 15, 2026
Europe charges importers for the carbon in their products. In the industries that run on electricity, it ignores the carbon in the electricity. That exemption is borrowed from a European subsidy and ends when the subsidy changes, which makes it a drafting problem for anyone signing a fifteen year power contract.
July 14, 2026
An illustrative benchmark of what a 500 MW load at a 95 percent load factor pays for delivered power across the seven organized markets. Wholesale prices cluster between 30 and 55 dollars per MWh. Delivered, the displayed totals run from about 36 to about 87.
July 2, 2026
The best way to energize early is not fixed. It moves with what your load earns, and on the illustrative case it changes twice: once at about $49 per MWh and again at about $114.
June 15, 2026
Published cost curves rank technologies by dollars per megawatt-hour at the plant gate. A firm-power buyer pays for a firm megawatt, delivered at a site, on a date. Three adjustments reshape that comparison and reorder the ranking.
April 15, 2026
Value it as a bundle: existing cash flow, generation interconnection and electrical infrastructure, a permitted industrial site near transmission, and large-load development potential. The operating economics set the base case; the site and its options are the upside.
Lane
How the market is structured, and what that changes about your next decision.
September 11, 2026
Across the 57 plans priced this way, that is the median at 1,000 kWh against the median at 500. The difference is how much you use that month. I downloaded all 1,053 plans on the state's Power to Choose site to find out how common this is.
August 17, 2026
Their targets differ, but what sits underneath them matters more. Each company built a different position, and each one carries a different cost, a different dependency and a different way of failing.
August 9, 2026
GE Vernova has more gas turbine capacity reserved than sold: 63 GW of held production slots against 53 GW of signed orders. Holding a slot is not the same as buying a turbine, and that difference is what the headline number hides.
July 21, 2026
The developer and buyer each need evidence created by the other's commitment, while grid rules adapt on a slower clock.
July 14, 2026
A data center may pay for its connection while leaving customers to pay for the wider grid. The real question is who pays beyond the substation.
June 30, 2026
For anyone siting or financing AI infrastructure: new AI hardware arrives on a two-year cycle while the delivery infrastructure built for it is financed for decades. Firm megawatts are necessary but interchangeable; the harder thing to secure is delivery that can absorb several hardware generations without a major retrofit.
Reference
Rule changes as they landed, oldest first, so you can see how the Texas large-load framework actually moved.
March 20, 2026
For developers and large power buyers: Texas proposed cutting the upfront security from $100,000 to $50,000 per megawatt.
April 24, 2026
For developers planning 2027-2028 gas builds and infra funds valuing gas platforms: GE Vernova's Q1 disclosures reprice equipment risk.
July 8, 2026
For developers with queue positions and offtakers structuring around them: what the new $50,000 per MW default financial security means for deal math.
Questions, corrections or disagreement on any of this are welcome: kris@tafelpower.com