Tafel Power

Markets

Firm gas across the seven US ISOs, reconciled from each market's own interconnection queue and the federal generator inventory.

The same question runs through every market: how much firm gas can a large load actually contract, and how. The answer splits on market structure. In energy-only, merchant ERCOT, the interconnection queue is a real supply signal: it holds 8.8 GW of signed, near-term merchant gas, the strict screened floor: merchant projects with a signed interconnection agreement and near-term operation. A broader, probability-weighted read of the same ERCOT queue is about 19 GW, and the headline nameplate is 69.7 GW. In the regulated markets, the queue is nearly empty of new gas because the utilities build through resource plans, not merchant queue positions.

Read the interconnection queue in Texas. Read the utility everywhere else.

See the ERCOT gas queue reconciliation and methodology.

Signed, near-term merchant gas in each ISO's interconnection queue: ERCOT 8.8 GW, SPP 2.0, PJM 0.7, MISO 0.4, others near zero
Signed, near-term (2026 to 2028) gas in each ISO's queue, reconciled. Analysis: Tafel Power.
MarketSigned, near-term gasExisting gasPlanned gasStructure
ERCOT8.8 GW60 GW3.5 GWEnergy-only, merchant
SPP2 GW33 GW6.9 GWRTO, largely regulated utilities
PJM0.7 GW95 GW5.8 GWCapacity market, mixed merchant and regulated
MISO0.4 GW74 GW15.1 GWMostly regulated, vertically integrated utilities
CAISO~0 GW29 GW~0 GWRegulated, decarbonizing
NYISO~0 GW24 GW~0 GWRegulated, decarbonizing
ISO-NE~0 GW15 GW~0 GWRegulated, constrained

One market sits outside the ISOs and dwarfs them: the regulated Southeast (Georgia Power, TVA, and their peers) holds roughly 181 GW of existing gas, more than any organized market. That capacity is utility-owned, so a data center reaches it through the utility on a regulated timeline, not through a merchant queue. It is why Georgia is one of the hottest data-center destinations, and it does not appear in any queue.

Signed, near-term merchant gas is Tafel Power's filtered estimate from each ISO's own queue (signed interconnection agreement, in service 2026 to 2028, merchant), not an ISO-published category. For ERCOT, this 8.8 GW is the strict floor; the broader ~19 GW risk-adjusted estimate applies Tafel Power judgment-based probability weights, not ERCOT-assigned probabilities. Existing and planned gas are from EIA-860M. Figures reflect mid-2026 snapshots and may have changed since.