Tafel Power

Ohio's Gas Queue Looks Empty Because Ohio Already Built Its Gas

Ohio's queue holds about 0.9 GW of signed gas, essentially one project, because the state already built about 6.4 GW during the Utica boom. Its strength for data centers is that existing fleet and nearby low-cost gas.

For hyperscalers · For infra funds · For developers · pjm · ohio · gas · utica · existing-fleet

Kris Narayanan · Tafel Power · April 30, 2026 · 2 min read


Read Ohio through its interconnection queue and you would skip the state. That is the mistake: Ohio already built its gas.

Ohio front-loaded its gas in the Utica boom

From 2015 to 2025, during the Utica shale buildout, Ohio added about 6.4 GW of new gas generation (net-summer capacity; about 7.2 GW nameplate), so roughly 6.4 of its 16.4 GW of existing gas is post-2015. That is why the queue looks empty: the combined-cycle build that other markets are still trying to queue, Ohio largely completed last decade, next to the wellhead gas that fuels it. The queue-only lens, which works in a still-building merchant market, understates a market that already built.

The demand is here too

Ohio is not a quiet market on the demand side. Through the AEP zone and the Columbus data-center cluster, it is PJM's number two zone for forecast peak growth. So Ohio pairs installed dispatchable capacity, comparatively low-cost Utica gas, and a top-tier data-center demand hub.

What this changes for the buyer

Hyperscaler energy leads. For a campus evaluating gas-backed firm power, eastern and central Ohio deserve a closer look than the empty queue suggests. The relevant analysis is existing-fleet headroom, gas supply from the Utica, and behind-the-meter or existing-plant offtake, not a new queue position.

Infra funds. The Ohio opportunity is around installed and uprate-able capacity near low-cost fuel and rising demand, not a merchant new-build queue thesis. Diligence the existing asset and its fuel logistics.

Existing fleet capacity is not the same as available contractual headroom. Buyers must also test capacity obligations, transmission deliverability, fuel availability, outage performance, and utility service requirements.

Methodology

The 0.9 GW signed-gas queue figure is reconciled from PJM's public New Services Queue (PlanningQueues feed) for Ohio: gas with an executed interconnection agreement, progressing, not already operating. Existing and recently built gas capacity, including the 2015 to 2025 additions and the roughly 16 GW total, are from EIA-860M (the federal monthly generator inventory), by state and operating year. Demand-growth ranking is from PJM's 2026 Load Forecast Report. These are Tafel Power's filtered estimates from public sources, not ISO-published categories. Figures reflect early-2026 snapshots and may have changed since.

All data compiled by Tafel Power from public sources. Framing informed by the firm's transaction advisory work in ERCOT and cross-ISO markets.


Share on LinkedIn

Questions, corrections or disagreement on any of this are welcome: kris@tafelpower.com

More from Insights

April 24, 2026

The Turbine, Not the Interconnection Queue, Now Gates 2028 Gas

GE Vernova's turbine slot reservations rose from 43 GW to 56 GW in the first quarter of 2026, with new orders expected to price 10 to 20 percent higher. For 2027 and 2028 gas, a secured turbine now matters as much as an interconnection agreement.

April 15, 2026

What a Legacy Biomass Plant Is Actually Worth

A legacy biomass plant's grid connection, switchyard, permits and site near transmission can be worth more than its thin power margins, though using that connection to serve a data center still needs its own study.